AI data center power shortage: the world and the US, 2026 to 2028
By 2028 power becomes the main limit on deploying AI compute, ahead of memory, our estimate. At least 16 GW of data center capacity is due online worldwide in 2026, and only about 5 GW of it is under construction, estimate (Sightline Climate)[1][2]. In the US, as much as 12 GW is due in 2026 and a third of it is under construction, estimate (Sightline Climate, via Bloomberg)[3]. Generator step-up transformers took more than 160 weeks to deliver by the first quarter of 2026 (Wood Mackenzie, via Reuters)[4].
The world: most of the 2026 pipeline is not under construction
- At least 16 GW of data center capacity across roughly 140 projects is due online in 2026, estimate (Sightline Climate, 24 February 2026)[1][2].
- About 5 GW of it is under construction[1][2]. About 11 GW is still in the announced stage, with no visible construction[1][5].
- 30-50% of the capacity due in 2026 is likely to be delayed, estimate (Sightline Climate)[1][2][5].
These are worldwide figures. Retellings often attach them to the US; the US figures are below.
The US: the 2026 pipeline and the grid queue
- “Data centers consuming as much as 12 gigawatts of power are supposed to come online in 2026 in the US”, and “only a third of that is currently under construction”, estimate (Sightline Climate, as reported by Bloomberg, 1 April 2026)[3]. Bloomberg adds: “Almost half of the US data centers planned for this year are expected to be delayed or canceled.”[3]
- Currence (formerly Sightline Climate) estimates that 55% of the announced 2026-2030 US data center pipeline is unlikely to come online (Q3 2026 Data Center Outlook, 27 August 2026)[6][7].
- US data center demand reaches up to 74 GW by 2028, with a shortfall of about 49 GW, estimate (Morgan Stanley, 27 February 2026)[8]. The bank has revised the figures since; the newer ones are known only from retellings, and those differ[9].
- In Texas, about 226 GW of large loads waited for a grid connection with ERCOT, the state’s grid operator, in November 2025, against 63 GW at the end of 2024; more than 70% of it is data centers[10]. Large-load applications reached 445.8 GW through 2033, but for 321 GW no studies had been submitted to ERCOT (Data Center Frontier, 31 August 2026)[11].
Equipment: transformers take years
- In the second quarter of 2025 power transformers took about 128 weeks on average to deliver, and generator step-up transformers, which connect power plants to the grid, 143 weeks (Wood Mackenzie)[12].
- By the first quarter of 2026, generator step-up transformer lead times “surpassed 160 weeks”, against an average of 143 weeks in 2024 (Reuters, citing Ben Boucher of Wood Mackenzie)[4].
A site that still waits for its transformer cannot take GPUs on the date its building is finished, our estimate.
Racks: more power per rack
- A Vera Rubin rack draws about 234 kW, up from an earlier 149 kW, estimate (Morgan Stanley, via BigGo)[13].
- Kyber NVL576 racks, due in 2027, are reported at about 600 kW[14].
A data hall built for the last generation often lacks the power per rack for the next one, so the sites that can host new systems are fewer than the megawatt totals suggest, our estimate.
What this means for buyers
- Powered space is the scarce part. With a third of the planned US capacity under construction[3], a site whose power is already energized is worth more than one with a power date on paper, and its price holds, our estimate.
- Ask for the energization date, not only the GPU delivery date. Lead times for generator step-up transformers, which connect power plants to the grid, grew to more than 160 weeks by early 2026[4]; new generation and grid connections cannot catch up in 2027, our estimate.
- Book 2027 and 2028 earlier. Rack power climbs to about 234 kW for Vera Rubin, estimate (Morgan Stanley)[13], and the sites ready for it go first, our estimate.
Waiting for more capacity means waiting for power that is not built yet.
Method and sources
This page is one part of our review of AI compute supply bottlenecks, which ranks the constraints on AI compute supply now, in 2027 and in 2028. The other two topic pages: HBM and server memory in 2027 and CoWoS capacity.
Figures in our facts registry were checked against their sources on 27 November 2026. Where only a retelling exists, the page names whose retelling it is. Analyst estimates and press reports carry their author’s name, so they are not mistaken for what the companies themselves said; our own judgment is marked “our estimate”.
Ancapex introduces companies that need reserved GPU capacity to the operators that have it. How we are paid is in our methodology.
Sources
- Sightline Climate (currence.ai): 2026 Data Center Outlook (24 Feb 2026)
- Up to half of the world's data centers may be delayed this year (Latitude Media, 24 Feb 2026)
- America's AI Build-Out Hinges on Chinese Electrical Parts (Bloomberg, 1 Apr 2026, archived copy)
- US power companies scramble to secure equipment as data center demand surges (Reuters via Kitco, 9 Jul 2026)
- Sightline Climate launches PowerStack newsletter (press release in Utility Dive, 5 Mar 2026)
- Currence (formerly Sightline Climate): Data Center Outlook Q3 2026 (report page)
- Hyperscaler Capex Is Up Because of Component Prices, Not Compute Ambitions (Currence blog, 27 Aug 2026)
- Powering AI: Energy Market Outlook 2026 (Morgan Stanley, 27 Feb 2026)
- Morgan Stanley: 70 GW data center power shortfall (Crypto Briefing, 1 Nov 2026)
- ERCOT's large load queue has nearly quadrupled in a single year (Latitude Media, 3 Dec 2025)
- ERCOT puts Texas AI megawatts to the test (Data Center Frontier, 31 Aug 2026)
- Mind the gap: tackling supply chain challenges in the electric T&D sector (Wood Mackenzie, 15 Oct 2025)
- Morgan Stanley on rack power and energy (BigGo Finance)
- NVIDIA GPU Roadmap 2026-2030: Rubin, Rubin Ultra, Feynman (VRLA Tech)