AI compute supply bottlenecks: November 2026 and the outlook to 2028
Memory is the tightest constraint on AI compute right now: HBM, and the server DRAM that HBM takes capacity from. From late September to the end of October SK hynix, Samsung and Micron confirmed the 2027 shortage themselves[1][2][3]. CoWoS packaging is third: the gap between demand and supply is narrowing[4], and TSMC's CoWoS capacity is estimated to double by the end of 2028[5]. By 2028 power becomes the main limit on deployment: grid access and electrical equipment. Hardware that mostly avoids the TSMC N3/N2, CoWoS and HBM chain exists and ships, but its edge is narrow: it works for inference and decode, and it is almost always paid for in more chips, racks and megawatts.
What this means for buyers
- HBM and server memory for 2027 are sold out. SK hynix has locked more than 50% of its 2027 and 2028 capacity into long-term contracts and expects demand above supply until 2030 (28 October 2026)[1]. Samsung expects AI demand in 2027 to “far exceed the industry supply” and calls its 2027 HBM “effectively sold out” (29 October 2026)[2][6]. Micron has contracted “the vast majority” of its 2027 HBM bits and expects memory and storage supply and demand to be “much tighter in calendar 2027 and 2028 than they were in 2026” (30 September 2026)[3].
- Price growth is slowing. TrendForce expects DRAM contract prices to keep rising, by less each quarter, as the gap between supply and demand narrows (18 November 2026)[7]. For 2027 it expects the increases to narrow further and level off in the second half of the year, and in its base case conventional DRAM contract prices decline in 2028, estimate (TrendForce, 25 November 2026)[8][9]. On 27 November TrendForce set out two scenarios: in its base case DRAM supply shortages ease in 2028, with “contract prices declining across all product categories beginning in 1Q28”; in its bear case conventional DRAM contract prices could “reverse course and begin declining in 4Q27, with price declines widening in 2028”, estimate (TrendForce, 27 November 2026)[10]. NAND gets cheaper from the first quarter of 2027, estimate (TrendForce, 19 November 2026)[11]. The shortage is real, but it is no longer growing.
- Data centers run behind plan. At least 16 GW of data center capacity was due online worldwide in 2026; about 5 GW is under construction, and about 11 GW is still announcements, estimate (Sightline Climate)[12][13]. In the US, up to 12 GW is due in 2026 and a third of it is being built (Bloomberg, citing Sightline)[14]. Generator step-up transformers took 143 weeks to deliver in the second quarter of 2025 (Wood Mackenzie)[15], and more than 160 weeks by the first quarter of 2026 (Reuters)[16].
- New GPUs wait longer. Lead times for new B300 orders run 26 to 40 weeks, against 14 to 26 weeks for GB300, reported by TrendForce, citing Commercial Times (25 November 2026)[17].
Memory for 2027 is largely contracted, and power is not built yet. In TrendForce’s base case memory gets cheaper only from early 2028; in its bear case prices could start falling in late 2027[10]. Waiting is a bet on the bear case, our estimate.
Ranking: now, 2027, 2028
The constraints on AI compute supply in order, from the sources in the sections below. Memory leads through 2027, power takes first place in 2028, and CoWoS drops to fifth. The order is our estimate.
| Rank | November 2026 | 2027 | 2028 |
|---|---|---|---|
| 1 | HBM and server DRAM | HBM and server DRAM | Power |
| 2 | Power and transformers | Power | HBM (HBM4E, 16-Hi) |
| 3 | CoWoS-L | TSMC N3/N2 nodes (prices) | TSMC nodes (N2, A16) |
| 4 | TSMC N3/N2 wafers | Optics (1.6T, EML, CPO) | Optics and CPO |
| 5 | Optics (EML) | CoWoS (demand about +80%[18]) | CoWoS (about 260,000 wafers a month[5]) |
| 6 | T-glass and substrates | Substrates and materials (materials up to 20% short[19]) | Substrates |
| 7 | Export controls (first for China) | Export controls | Export controls and Taiwan |
Bottleneck by bottleneck
Two or three facts for each link in the chain, and what each means for a team that rents GPU capacity.
Memory: HBM and server DRAM
- SK hynix holds 50% of the HBM market, Samsung 33% and Micron 18%, estimate (Counterpoint, second quarter of 2026)[20]. Memory inventories at Samsung and SK hynix are below 10 days, estimate (KB Securities, 7 September 2026)[21].
- The average HBM price rises 121% year on year in 2027, estimate (TrendForce, 29 September 2026)[22]. DRAM prices rise about 20% quarter on quarter in the fourth quarter of 2026, against about 80% in the second and about 40% in the third, estimate (TrendForce, citing Commercial Times)[23].
- One HBM4 wafer takes the capacity of three ordinary DRAM wafers, estimate (KB Securities)[24]. Micron puts the ratio at about 3× for HBM3E against DDR5 and says the gap widens with every generation[25].
What it means for buyers: HBM pulls capacity away from ordinary DRAM, so servers built on LPDDR, GDDR or DDR5 ride the same price wave. HBM gets more expensive in 2027, and DRAM prices keep rising, only more slowly.
Deep dive: HBM and server memory shortage in 2027
Power and data centers
- 30-50% of the data center capacity due in 2026 is likely to be delayed, estimate (Sightline Climate)[12][13][26]. About 226 GW of large loads waited in the ERCOT grid connection queue in November 2025, against 63 GW at the end of 2024; more than 70% of it is data centers[27].
- US data center demand reaches up to 74 GW by 2028, with a shortfall of about 49 GW, estimate (Morgan Stanley, 27 February 2026)[28]. The bank has revised the figures since; the newer ones are known only from retellings, and those differ[29].
- A Vera Rubin rack draws about 234 kW, up from the bank's earlier 149 kW, estimate (Morgan Stanley, via BigGo)[30]. Kyber NVL576 racks in 2027 are reported at about 600 kW[31].
What it means for buyers: the date a site has its power energized matters as much as the date its GPUs arrive. Designs with more tokens per watt gain.
Deep dive: AI data center power shortage, the world and the US
Packaging: CoWoS
- The gap between CoWoS demand and supply narrows from about 20% to about 10% by the end of 2026, estimate (institutional investors, via TrendForce, June 2026)[4]. CoWoS-L is the scarcest variant: NVIDIA and AMD accelerators have already moved to it, per TrendForce[32].
- TSMC CoWoS capacity reaches 115,000-140,000 wafers a month at the end of 2026, about 130,000 by consensus, estimate (Economic Daily News, TechNews)[33], and about 260,000 at the end of 2028, estimate (Economic Daily News, via TrendForce)[5]. Goldman Sachs is higher: an average of about 290,000 a month in 2028, estimate (Goldman Sachs)[34].
- Demand grows from 1.394 million wafers in 2026 to 2.509 million in 2027, about +80%, estimate (Morgan Stanley, September 2026)[18].
What it means for buyers: packaging is no longer the first constraint, but with demand up about 80% in 2027[18] it is not solved, and CoWoS-L, used by the newest NVIDIA and AMD GPUs, stays the tight variant.
Deep dive: CoWoS capacity 2026 to 2027
Chipmaking: TSMC N3 and N2
- N3 wafer prices rise up to 15% in the second half of 2026 and a further 5-10% in 2027, reported (Commercial Times, via TrendForce)[35].
- N3 output is about 130,000 wafers a month in early 2026[35] and reaches 210,000 by mid-2027; N2 reaches 110,000 by mid-2027, reported[5]. An N2 wafer costs about $30,000[36][37].
- TSMC spends $60-64 billion on capital equipment in 2026, 70-80% of it on advanced nodes[5].
What it means for buyers: the node sets price and queue, it does not block supply. Wafer price increases flow into the cost of new GPUs, and large GPUs and ASICs have no alternative to N3/N2 before 2027-2028.
Substrates and optics
- Nittobo makes about 90% of T-glass[38]. Supply falls 10-20% short in 2026, prices are up 20-30%, and lead times for CCL laminate went from 8-10 weeks to more than 20[38][39]. Nittobo's new plant in Fukushima starts shipping in July 2027[40], and analysts expect the shortage to last at least to the end of 2027[41].
- The chairman of Unimicron warns that key materials (glass cloth, CCL laminate, ABF) could fall 20% short in 2027, with lead times for some equipment up to 30 months[19].
- On 2 March 2026 NVIDIA invested $2 billion each in Lumentum and Coherent and secured their capacity; other buyers get supply after 2027, reported[42]. 800G transceivers fall 40-60% short of demand until 2027, and 1.6T transceivers 30-40% short until 2029, estimate (McKinsey, via TechTimes)[42].
What it means for buyers: these are the quiet constraints. They hit GDDR and LPDDR alternatives on organic substrates too, and T-glass relief comes no earlier than the end of 2027.
Export controls
- The BIS rule of 15 January 2026 reviews H200, MI325X and weaker chips case by case (TPP under 21,000, DRAM bandwidth under 6,500 GB/s). Shipments to China and Macau are capped at 50% of shipments to US customers, and companies headquartered in China or Macau face a presumption of denial[43][44].
- The AI OVERWATCH Act, a two-year ban on Blackwell for China, is still a bill; a House committee approved it 42 to 2[45].
- China suspended its ban on exports of gallium, germanium and rare earths to the US from 9 November 2025 to 27 November 2026, and kept licensing[46]. On 24 November 2026 its Ministry of Commerce extended the suspension for gallium, germanium, antimony and superhard materials from 28 November 2026 to 27 January 2027[47][48]. China’s rare earth export controls of October 2025 stay suspended until 10 January 2027, by a notice of the Ministry of Commerce and the customs administration of 9 November 2026[49][50].
What it means for buyers: for Chinese vendors the limit is absolute; elsewhere it is a tail risk. The whole N3/N2 and CoWoS chain sits in Taiwan[51][52].
Hardware that sidesteps the shortage
Some accelerators avoid HBM, CoWoS or TSMC's leading nodes. Each pays for it elsewhere, and the shortage moves with it. The verdicts are our estimate.
| Hardware | The price of the sidestep | Where the shortage moves | Verdict to 2028, our estimate |
|---|---|---|---|
| Cerebras WSE-3 | 44 GB of SRAM on the wafer[53]: large models need many CS-3 systems and outside memory | TSMC N5 wafers and megawatts: 700 MW under contract on 30 September 2026[54] | Viable. $26.1 billion of remaining performance obligations[54], OpenAI at 750 MW[55]; the risk is a few customers bringing most of the revenue[55] |
| NVIDIA Groq 3 LPX | 256 chips hold only 128 GB of SRAM; large models need many racks or a pairing with NVL72; no training[56][57] | Samsung 4 nm, reported close to full load[58]; DDR5; racks | Viable as a complement, not a replacement |
| Tenstorrent Blackhole | GDDR6 at 512 GB/s, 10-40 times below HBM; no MLPerf results[59] | GDDR and DRAM prices | Niche: wins on price and availability |
| d-Matrix Corsair | 2 GB of SRAM, inference only[60] | LPDDR | Niche, promising: shipping since summer 2026[61] |
| Qualcomm AI200, AI250 | 768 GB per card[62], but low bandwidth per user and young software | LPDDR, shared with phones and CPUs | Viable with conditions; AI250 samples in 2027[63] |
| Intel Crescent Island | 160 GB of LPDDR5X[64], low bandwidth, sampling only | LPDDR5X | A bet on 2027, not proven |
| Taalas | One model per chip; a new model means a new tape-out | Mask cycles | Part of AMD since 17 November 2026[65][66] |
| Huawei and China | About 2 years behind, about 4 Huawei GPUs per NVIDIA GPU, words of DeepSeek's founder on a July 2026 investor call, from a retelling of a leaked transcript[51] | SMIC yields of 25-46% at 7 nm and 15-36% at 5 nm[67]; HBM; power | Viable only inside China |
Where the shortage moves
- SRAM designs (Groq, Cerebras, d-Matrix) take the load off HBM and CoWoS and put it on logic wafers, racks and megawatts. Samsung 4 nm, where Groq 3 is made, is reported almost fully loaded[58].
- LPDDR and GDDR designs use fewer wafers per gigabyte: one HBM4 wafer equals three DRAM wafers, estimate (KB Securities)[24]. They still land in the 2027 server DRAM shortage: the gain is availability, not price.
- Samsung and Intel as a second fab. Products already ship, such as Groq 3 on Samsung 4 nm[68], but large new capacity for AI chips arrives only in 2027-2028: Samsung's Taylor fab in volume in 2027[69], Intel 14A in 2028[70].
What changed by November 2026
- Vera Rubin ships. NVIDIA ships Vera Rubin NVL72, generally available on OCI and Google Cloud A5X; its data center revenue for the third quarter of fiscal 2027 was $107.6 billion (Form 8-K, 17 November 2026)[71].
- Maia 300 moves to TSMC. Microsoft announced Maia 300 on TSMC N2P with 288 GB of HBM4 (12 October 2026)[72], deployed from 2027[73]. Earlier reports had the next Maia on Intel 18A[74].
- AMD owns Taalas. AMD closed the purchase on 17 November 2026[65]; the technology goes into the Instinct line[66].
- Rubin CPX is gone. NVIDIA took it off its roadmap in March 2026[75][76].
- Morgan Stanley revised CoWoS demand. In September the bank cut its 2027 forecast to about 2.509 million wafers, about +80% instead of +93% in its summer version, estimate (Morgan Stanley)[18][77].
- Memory makers confirmed the 2027 shortage, while DRAM price growth slows[1][2][3][7].
What to watch
- TSMC CoWoS capacity against the target of about 130,000 wafers a month by the end of 2026[33], and the AP7 and Arizona sites.
- Contract prices of DRAM, HBM, LPDDR and NAND (TrendForce); memory inventories at Samsung and SK hynix, below 10 days by the estimate of KB Securities[21]; memory makers' capital spending.
- HBM4 12-Hi and 16-Hi yields, the timing of HBM4E, CXMT qualification.
- Customers of Intel EMIB-T, 14A and 18A-P; trial production at Samsung Taylor.
- Volumes of 1.6T transceivers and 200G EML lasers, adoption of CPO; Nittobo's Fukushima plant, shipping from July 2027[40].
- ERCOT and PJM grid connection queues; transformer lead times.
- BIS rules and the AI OVERWATCH Act, H200 licenses; shipments of Huawei Ascend 950DT; China's decision on rare earth exports after 10 January 2027 and on gallium, germanium and antimony after 27 January 2027[47][49].
- Cerebras revenue against its plan to triple it in 2027[54]; LPX deployments beyond Nebius and Groq[78][79].
Scenarios to 2028
Three ways the next two years can go. The probabilities and effects are our estimate.
| Scenario | Triggers | Effect |
|---|---|---|
| Easing about 25%, our estimate | A pause in capital spending, orders moved between buyers (as with TPU), fast HBM4 yields, T-glass ahead of schedule | HBM eases at the end of 2027; CoWoS clears by 2027; power is first |
| Base about 55%, our estimate | TSMC and memory makers deliver their plans; demand follows Morgan Stanley's estimate | HBM first in 2027, power first in 2028; sidestep hardware grows in the inference niche |
| Tightening about 20%, our estimate | Trouble with HBM4 or HBM4E, tighter export controls, a crisis around Taiwan, grid failures | DRAM and HBM prices 1.5× or more; Samsung, Intel and SRAM designs gain value; a Taiwan crisis stops everyone who depends on TSMC and CoWoS, while Samsung-made chips (Groq 3 LPX, Rebellions) and the SMIC ecosystem are hit less, though LPX runs alongside Vera Rubin and some substrates are made in Taiwan |
Appendix: every accelerator and its dependencies
The full list of data center AI accelerators and a matrix of how much each depends on every bottleneck.
Data center AI accelerators
Companies rarely disclose packaging (NVIDIA for Blackwell, Microsoft for Maia 100, Intel for Gaudi 3, FuriosaAI and Rebellions do). Elsewhere packaging and fabs are an estimate, and the cell names whose. “Standard, our estimate” marks chips without HBM whose packaging no source names. “No data”: no source we checked gives it.
Merchant GPUs and platforms
| Product | Fab and node | Packaging | Memory | Workload | Status |
|---|---|---|---|---|---|
| NVIDIA B200, GB200 | No data | CoWoS-L (Jensen Huang)[80] | About 180 GB HBM3E per GPU on HGX B200 (1.4 TB per 8 GPUs); 372 GB per GB200 superchip of two GPUs[81][82] | Training and inference | Shipping |
| NVIDIA B300, GB300 | No data | CoWoS-L, estimate (TrendForce)[83] | 288 GB HBM3E, reported[31] | Training and inference | Shipping; about 400,000 GB300 reserved by clouds for late 2025 and early 2026 (Taiwan Economic Daily via TechPowerUp, October 2025)[84] |
| NVIDIA Vera Rubin NVL72 | TSMC N3, reported; NVIDIA does not name the node[31] | CoWoS-L, estimate (TrendForce, Morgan Stanley)[32][85] | 288 GB HBM4, reported[31] | Training and inference | Shipping, generally available on OCI and Google Cloud A5X; NVIDIA data center revenue of $107.6 billion in the third quarter of fiscal 2027 (Form 8-K, 17 November 2026)[71]. The 8-K of 26 August 2026: “full production”, CoreWeave, Google Cloud, Azure, OCI, Nebius[86] |
| NVIDIA Rubin CPX | No data | No data | GDDR7[76] | Prefill | Dropped: off NVIDIA's roadmap in March 2026; per Ian Buck of NVIDIA (as retold by Wccftech), the idea moves to the Feynman generation[75][76] |
| NVIDIA Rubin Ultra (Kyber NVL576) | TSMC N3P, estimate (Commercial Times via TrendForce)[87] | CoWoS-L, estimate (same source)[87] | HBM4E, a rumor[87] | Training | Announced for 2027[87]; second half of 2027 and about 600 kW per rack, reported[31]. Per Commercial Times, two dies per package are planned, and four dies and HBM4E are rumors[87] |
| NVIDIA Groq 3 LPU, LPX | Samsung 4 nm[68][75][88] | No HBM | 500 MB SRAM per chip; 128 GB SRAM and 12 TB DDR5 per rack[89] | Decode | Shipping, “full production” (8-K)[86][90]; first users Nebius and Groq[78][79]; a deal of about $20 billion: a non-exclusive license and part of the team moving over, Groq stays independent[75][91] |
| AMD MI355X | TSMC N3P and N6[92] | CoWoS-S, reported by TweakTown; AMD writes only of 3D packaging[92] | 288 GB HBM3E[92] | Training and inference | Shipping (AMD 8-K of 4 November 2025: demand for MI350, Vultr opened access to MI355X)[93] |
| AMD MI450, MI455X (Helios) | TSMC N2 and N3 (AMD, as retold by TrendForce)[94] | CoWoS-L, estimate (Tom's Hardware via TrendForce)[94] | 432 GB HBM4, reported (AMD's release gives no memory figures); bandwidth of 19.6, 22.3 or 23.3 TB/s depending on the source[94][95][96] | Training and inference | Shipping: on 23 July 2026 AMD announced “now in production”, shipments from the end of the third quarter; per the 8-K of 3 November 2026, Anthropic, Meta, Microsoft, OpenAI and OCI already run on the first Helios racks, data center segment $8.5 billion, ramp in the fourth quarter[97]; per The Next Platform (as retold by shattered.io, October 2026), volume production not before the second quarter of 2027[95]. OpenAI (6 GW, 1 GW in the second half of 2026), Oracle (50,000)[98][99][100]; Morgan Stanley forecasts 1 million MI455 and 0.5 million MI450 in 2027[77] |
| Intel Gaudi 3 | TSMC N5[101] | 2.5D (Intel)[101] | 128 GB HBM2E[101] | Inference and training | Shipping, limited (IBM Cloud)[63] |
| Intel Crescent Island | Not disclosed[64] | Standard, our estimate | 160 GB LPDDR5X (up to 480 GB from ODMs)[64] | Inference | Sampling in the second half of 2026; 350 W, PCIe, air cooled[64] |
| Intel Jaguar Shores | Not disclosed (Intel 10-K)[102] | No data | No data | Rack scale | Announced for 2027 (reported by Tom's Hardware)[103] |
ASICs of hyperscalers and AI companies
| Product | Fab and node | Packaging | Memory | Workload | Status |
|---|---|---|---|---|---|
| Google TPU v6e Trillium | TSMC N5, estimate (SemiAnalysis)[104] | CoWoS, estimate (Morgan Stanley, for TPUs overall)[85] | 32 GB HBM (Google: Ironwood has six times as much)[105] | Inference and training | Shipping |
| Google TPU v7 Ironwood (Broadcom and MediaTek) | TSMC N3P, estimate (Data Gravity)[106] | CoWoS, estimate (Data Gravity, Morgan Stanley)[106] | 192 GB HBM3E[104][105] | Inference and training | Shipping: generally available since 31 March 2026 per Google Cloud release notes (preview from 24 November 2025)[107]; 2026 output of 2.7 million TPU v7x alone (SemiAnalysis, as retold)[108], of all TPUs 3.3 million (DigiTimes) or 4.5-4.6 million (GF Securities, BofA), reported[106]; the v7x and all-TPU figures do not compare directly |
| Google TPU 8t “Sunfish” (Broadcom) | TSMC N2 per TheNextWeb, the N3 family per Tom's Hardware (estimates differ)[109][110] | CoWoS per Commercial Times (via Wccftech); TrendForce expects Google to move to EMIB-T in 2027[32][111] | 8 stacks of HBM3E 12-Hi[109] | Training | Announced for late 2027[109] |
| Google TPU 8i “Zebrafish” (MediaTek) | As TPU 8t: N2 or N3[109][110] | As TPU 8t | 6 stacks of HBM3E[109] | Inference | Announced for late 2027; 20-30% cheaper than the 8t training chip[109] |
| AWS Trainium2 | TSMC N5, estimate (The Register)[112] | CoWoS, estimate (SemiAnalysis: CoWoS-S or R)[113] | 96 GB of HBM (AWS); per SemiAnalysis, HBM3E stacks at HBM3 speeds[113][114] | Training and inference | Shipping |
| AWS Trainium3 | TSMC N3[115] | CoWoS; EMIB-T, reported[116] | 144 GB HBM3E[115] | Training and inference | Shipping: generally available since December 2025; “nearly fully subscribed”, Amazon custom silicon above a $20 billion run rate (reported by INDmoney)[115][117]; designed with Alchip and Marvell (TrendForce)[118] |
| AWS Trainium4 | TSMC, probably 2 nm (a guess by The Next Platform)[119] | No data | HBM, type not named: AWS promises twice the HBM capacity and 4 times the HBM bandwidth of Trainium3[119] | Training | Announced; “significant pre-orders” (reported by INDmoney)[117] |
| AWS Inferentia2 | 5 nm, fab not named (The Next Platform)[119] | Not disclosed | 32 GB HBM[120] | Inference | Shipping (legacy) |
| Microsoft Maia 100 | TSMC N5[121] | CoWoS-S (Microsoft)[121] | 64 GB HBM2E[121] | Training and inference (Microsoft)[121] | Internal use; no Maia 100 virtual machines were offered for rent on Azure (The Next Platform, 28 January 2026)[122] |
| Microsoft Maia 200 | TSMC N3P[122] | CoWoS-S, estimate (TrendForce)[32] | 216 GB HBM3E[123] | Inference | Shipping since 26 January 2026; GPT-5.2, Copilot[115][123] |
| Microsoft Maia 300 | TSMC N2P (Microsoft, 12 October 2026)[72] | No data | 288 GB HBM4[72] | Inference[124] | Announced, deployed from 2027[72][73]. Earlier reports had Maia 3 on Intel 18A[74] |
| Meta MTIA 200, 300-500 (Broadcom) | TSMC[125] | CoWoS-L on MTIA 400, estimate (TrendForce)[32] | No data | Recommendations, then generative AI | Shipping; about 180,000 units in 2026, estimate (presenc.ai)[125] |
| OpenAI chip with Broadcom (“Titan” in Korean industry reports)[115] | TSMC N3, reported[126] | CoWoS, estimate (Morgan Stanley: Broadcom has 10,000 wafers for OpenAI)[85] | HBM (Samsung HBM4, reported)[126] | Inference | Sampling: production at the end of 2026; 1.3 GW in 2027 (Broadcom)[115] |
| Tesla AI5 | TSMC and Samsung (Musk: “TSMC and Samsung will produce the chip”); per Korean Tech Texas, the TSMC part is on N2P, and Arizona belongs to AI6.5[127][128] | No data | Not disclosed | Inference and data center | Taped out on 15 April 2026; volume in the second half of 2027; on Tesla's third-quarter call (21 October 2026): AI5 goes into Optimus around April 2027[127][128] |
| Tesla AI6 | Samsung 2 nm (SF2, reported)[129] | No data | No data | Inference and training | A $16.5 billion contract; moved to the fourth quarter of 2027 or later (reported)[130][131] |
| Tesla Dojo, Dojo3 | TSMC N7, InFO-SoW[132][133] | Wafer level[132][133] | SRAM[133] | Training | Shut down in 2025; in January 2026 Musk restarted it as Dojo3 for compute in space[134] |
| ByteDance ASIC (Broadcom) | Samsung: talks on manufacturing (Reuters, February 2026; ByteDance called the report inaccurate)[135] | No data | No data | Inference[135] | Media reports; export controls[135] |
Start-ups and independents
| Product | Fab and node | Packaging | Memory | Workload | Status |
|---|---|---|---|---|---|
| Cerebras WSE-3 | TSMC N5, a whole wafer[53] | Its own wafer-scale design, no CoWoS[53] | 44 GB SRAM[53], no HBM | Fast inference | Shipping: IPO of $6.4 billion[136]; revenue in the second quarter of 2026 of $180.1 million GAAP, $210 million core[137]; third quarter $210.8 million GAAP, $230.9 million core; remaining performance obligations of $26.1 billion on 30 September 2026; 700 MW under contract; the company expects to triple revenue in 2027[54]; OpenAI 750 MW plus an option on 1.25 GW[55]; partnerships with AWS and AMD[137][138]; WSE-3T and the CS-4 rack announced on 19 August 2026[139] |
| SambaNova SN50 | TSMC 5 nm (datasheet)[140] | No data | 64 GB HBM2E, 432 MB SRAM and up to 2 TB DDR5 (datasheet; the product page says up to 512 GB)[140] | Agentic inference | Sampling in the second half of 2026; SoftBank Corp.[115] |
| Tenstorrent Blackhole, Galaxy | TSMC N6[141] | Standard, our estimate | 180 MB SRAM and 32 GB GDDR6[59] | Inference, development | Shipping: Galaxy generally available on 28 April 2026[142]; cores cut from 140 to 120 for yield[59] |
| Tenstorrent Quasar | Samsung SF4X[143] | Chiplets[143] | No data | Inference | Announced (2023 data)[143] |
| d-Matrix Corsair | TSMC N6[60] | Standard, our estimate | 2 GB SRAM and 256 GB LPDDR5[60] | Inference | Shipping: full production since June 2026, shipping in batches from the summer to selected hyperscalers, neoclouds and AI labs (company statement of 9 June 2026, no names)[61]; valued at $2 billion (reported by Bloomberg, November 2025)[144] |
| Etched Sohu | TSMC N4P (Etched site)[145] | Not disclosed (Etched: “advanced packaging”)[145] | HBM: 144 GB HBM3E per aiwiki, citing the 2024 announcement; the site now says “HBM/SRAM hybrid”[145][146] | Transformer inference | Sampling or shipping: racks in summer 2026, contracts above $1 billion; a Series C of $300 million at a $10.3 billion valuation (23 July 2026)[147]; then a $700 million round at $21 billion led by Jane Street (18 August 2026)[145][148] |
| MatX One | TSMC (reported by Sacra)[149] | Not disclosed (per Sacra, Alchip and Marvell handle packaging)[149] | HBM and SRAM[150] | No data | Announced: a Series B of $500 million (24 February 2026), tape-out promised within a year[150] |
| Positron Atlas, Asimov | Atlas: Altera Agilex-7M FPGA[151]; Asimov: ASIC | Standard, our estimate | Atlas: 32 GB HBM2e[151]; Asimov: LPDDR5X (the company, in EE Times)[151], up to 2.3 TB per chip[152] | Inference | Atlas shipping; Asimov 2027; a Series C of $875 million at a $5 billion valuation (10 September 2026)[144][152] |
| Taalas HC1 | TSMC N6 (Taalas site)[153] | Standard, our estimate | Weights in silicon[153] | Inference of one fixed model | HC1: a technology demonstrator[153]; AMD announced the purchase of Taalas on 6 August 2026 and closed it on 17 November 2026, the technology goes into the Instinct line[65][66] |
| Rebellions REBEL, ATOM | REBEL: Samsung 4 nm[154], next step SF2[155]; ATOM: Samsung 5 nm[156] | 2.5D Samsung I-Cube S[157] | REBEL: 144 GB HBM3E[158]; ATOM: no data | Inference | ATOM shipping; REBEL sampling, racks around 2027[59] |
| FuriosaAI RNGD | TSMC N5[159][160] | CoWoS-S (the company's Hot Chips 2024 talk, as retold by ServeTheHome)[159] | 48 GB HBM3[161] | Inference | Shipping: about 4,000 RNGD in production in 2026; customers LG AI Research, LG Uplus, Samsung SDS, MegazoneCloud (Korea Herald, 2 April 2026)[160] |
| Graphcore IPU (SoftBank) | TSMC N7[162] | Wafer-on-wafer[162] | SRAM and DDR4[162] | Training and inference | Legacy; the IPU pages are gone from its site[162][163] |
| Lightmatter Passage | GlobalFoundries (photonics, GF Fotonix)[164] | No data | None | Interconnect | Sampling: M1000 and an evaluation kit; volume shipments not confirmed[164][165][166] |
| Axelera Europa, Titania | Europa: Samsung 5 nm[167]; Titania: no data | Standard, our estimate | Europa: up to 64 GB per chip, type not named; Titania: 128 GB LPDDR6[167][168] | Edge and data center inference | Europa shipping (“Shipping now”, 15 September 2026)[169]; Titania: architecture published on 12 November 2026, production from the second half of 2027, figures still from simulation[168] |
Outside the data center market or out of the game: Blaize, EnCharge and Hailo work at the edge[170][171][172]; Mythic makes the M1 chip for the edge, but now pitches its chiplet platform “from edge to data center”[173]; under an agreement with AMD the Untether AI team moved to AMD, and the company stopped shipping and supporting its products (2025)[174]; Esperanto has ceased operations[175]; OpenAI bought the patents of Rain AI after takeover talks failed, most of its staff left and the company has almost stopped working (The Information, as retold by crypto.news, 6 August 2026)[176]; Extropic has the XTR-0 prototype[177]; Fractile plans a commercial tape-out at the end of 2026[59].
China
Chinese makers rarely disclose the fab, the packaging or the memory generation: neither Hygon's annual report nor Biren's prospectus gives them[178][179]. Unless the cell says otherwise, these columns are estimates of the industry press and analysts (The Substrate, TrendForce, SemiAnalysis)[180].
| Product | Fab and node | Packaging | Memory | Workload | Status |
|---|---|---|---|---|---|
| Huawei Ascend 910C | SMIC, 7 nm class, estimate (SemiAnalysis), plus some TSMC dies made before the sanctions (chip teardown per The Substrate)[180][181] | 2.5D (The Substrate)[180] | HBM2E from stockpiles; per The Substrate, China most likely ran out of stockpiled HBM in late 2025[180] | Training and inference | Shipping: more than 1,000 SuperPoDs; about 810,000 Ascend chips in 2025 (IDC via Reuters); a 2026 target of about 600,000 910C (Bloomberg)[51][180][182] |
| Huawei Ascend 950PR | SMIC N+3 or N+2 (estimates differ)[51][183] | 2.5D | 112 GB of HiBL 1.0, Huawei's own HBM (Atlas 350, TrendForce)[184] | Prefill | Debuted on 20 March 2026 (Atlas 350, 2.8 times faster than H20: Huawei's claim)[184]; per Reuters (via Khaleej Times, 29 April 2026), volume production from April, full shipments from the second half of 2026, large companies rushing to order; Huawei has not confirmed volumes[185] |
| Huawei Ascend 950DT | SMIC | 2.5D | 144 GB of HiZQ 2.0[182][186] | Decode and training | Huawei plans the fourth quarter of 2026; a SuperPoD of 8,192 chips[51][187]; per TrendForce (8 June 2026), deployment in Huawei Cloud was brought forward to August[188] |
| Huawei Ascend 960, 970 | SMIC | No data | Huawei's own HBM | Training | 960DT: first quarter of 2027 (reported); 970: fourth quarter of 2028[51][184][186] |
| Cambricon Siyuan 590, 690 | SMIC N+2, estimate (TrendForce)[189] | 2.5D | 590: 80 GB (per aiwiki; there is no official datasheet, and the HBM generation is not named)[190]; 690: 196 GB HBM3 (reported)[191] | Training and inference | Shipping: revenue in the first half of 2026 of RMB 5.996 billion, profit RMB 2.311 billion (reported by Big Hat Group); a target of about 500,000 (Bloomberg)[191] |
| Hygon DCU | Not disclosed: contractors make the wafers and the packaging (2025 annual report)[178] | Not disclosed | HBM, generation not disclosed[178] | HPC; training and inference[178] | Shipping: in more than 20 industries at the end of 2025[178] |
| Alibaba T-Head PPU, Zhenwu | Domestic 7 nm, fab not named (TrendForce)[192] | 2.5D[192] | PPU and Zhenwu 810E: 96 GB HBM2e; Zhenwu M890: 144 GB HBM, generation not named[192][193] | Training and inference | Shipping: 560,000 cumulative shipments (TrendForce, 21 May 2026)[193]; about 265,000-270,000 in 2025[180][194] |
| Baidu Kunlunxin P800 | No data | 2.5D (TechInsights)[195] | 96 GB HBM (UDN)[196] | Training and inference | Shipping: about 60,000 in 2025[180] |
| Biren BR106, BR166 | Chinese contractors; SMIC is not named in the prospectus[179] | 2.5D (prospectus)[179] | Two dies and four DRAM chips in one package, generation not disclosed[179] | OAM: training and inference; PCIe: inference[179] | Shipping: HKEX listing (January 2026); 4,500-10,000 in 2025[180] |
| Moore Threads MTT S5000 | Not disclosed | 2.5D | HBM, not confirmed: the company does not name the memory type[197] | Training and inference | Shipping: about 20,000 in 2025; revenue in the first half of 2026 up 147%[180][198] |
| MetaX C500, C600 | C500: historically TSMC (The Substrate); C600: not disclosed, SMIC as The Substrate assumes[180] | 2.5D | C600: 144 GB HBM3E[180] | Training and inference | Shipping: about 25,000 in 2025[180] |
| Enflame S60, L600 | S60: TSMC (reported by The Substrate); L600: no data[180] | 2.5D | No data | Inference | Shipping: about 60,000-70,000 S60 (Tencent); STAR Market IPO in September 2026[191][199] |
| Iluvatar CoreX | Not disclosed | 2.5D | 64 GB HBM on TianGai 150, generation not disclosed[200] | Training and inference: in the first nine months of 2025 about 10,000 cards for training and 14,000 for inference (The Substrate)[180] | Shipping: about 30,000 in 2025[180] |
| Tencent Zixiao 2.0 | No data | No data | No data | Training and inference (the 2.0 series, developed with Enflame)[201] | Internal use; a target of 100,000 cards by the end of 2026[201] |
Others and design partners
| Product | Fab and node | Packaging | Memory | Workload | Status |
|---|---|---|---|---|---|
| Qualcomm Cloud AI 100 Ultra | 7 nm (estimates of Flopper and SemiAnalysis; fab not named)[202] | Standard, our estimate | 128 GB LPDDR4x[203] | Inference | Shipping (the product is on Qualcomm's site)[203] |
| Qualcomm AI200 (Dragonfly AI200) | Not disclosed | Standard, our estimate | 768 GB LPDDR per card[62] | Inference | 2026; a 140 kW rack (Qualcomm's page; the release of 27 October 2025 said 160 kW)[204] |
| Qualcomm AI250, AI300 | No data | No data | LPDDR, 133 TB/s effective, as claimed[115] | Inference | Sampling in 2027 and 2028[63] |
| Design partner | For whom | CoWoS by Morgan Stanley, 2026 to 2027, thousand wafers |
|---|---|---|
| Broadcom | Google TPU (to 2031), Meta MTIA, OpenAI, Anthropic and 2 undisclosed customers ($6 billion of orders)[115][117] | About 300 to 484[205][206]; SemiAnalysis, as retold, gives 215 for 2026[108] |
| Marvell | AWS Trainium (Trainium3 together with Alchip, per TrendForce), Microsoft Maia, talks with Google; Celestial AI ($5.5 billion)[117][118][207][208] | 26 to 90 (the September version; the summer version had 17 to 64)[18][205][206] |
| MediaTek | Google TPU v7e and 8i[109][209] | 40 to 180[205][206] |
| Alchip | AWS Trainium3 (TrendForce)[118] | No data |
| GUC | Microsoft, presumably: Microsoft has not named its Maia 300 partner (The Next Platform)[124] | 14 to 60 (the summer version only, 36Kr)[205] |
Dependency matrix
H, M, L, none: high, medium, low or no dependency. TSMC node: N3 and N2 are H, N4 and N5 are M, N6 and older are L; n/a where the node is not disclosed. Resilience runs from 1-2, fully in the queue for TSMC, CoWoS and HBM; through 3, one link sidestepped, or the TSMC node and CoWoS sidestepped while HBM stays (HBM is bottleneck number one in this review); to 4-5, two or three links sidestepped including HBM, with a dependency on power, DRAM or both. A high dependency on export controls (H) takes one point off. Letters and scores are our estimate, not company data.
| Product | TSMC node | CoWoS | HBM | Substrates | Optics | Power | Export controls | Resilience |
|---|---|---|---|---|---|---|---|---|
| NVIDIA Rubin, Rubin Ultra | H | H | H | H | H | H | M | 1 |
| NVIDIA B300 | M | H | H | H | H | H | M | 1 |
| NVIDIA Groq 3 LPX (Samsung) | none | none | none | M | M | M | M | 4 |
| AMD MI355X | H | H | H | H | M | H | M | 1.5 |
| AMD MI450, MI455X | H | H | H | H | H | H | M | 1 |
| Intel Gaudi 3 | M | M | M | M | M | M | M | 2.5 |
| Intel Crescent Island | n/a | none | none | M | L | L | L | 4 |
| Google Ironwood, TPU 8 | H | H | H | H | M | H | L | 1.5 |
| AWS Trainium3 | H | H | H | H | M | H | L | 1.5-2 |
| Microsoft Maia 200 | H | H | H | H | M | H | L | 1.5 |
| Meta MTIA (new generations) | M or H | M | M | M | M | M | L | 2.5 |
| OpenAI (chip with Broadcom) | H | H | H | H | M | H | L | 1.5 |
| Tesla AI5, AI6 (TSMC and Samsung) | M | n/a | n/a | M | L | M | L | 3 |
| Cerebras WSE-3 | M | none | none | L | L or M | H | L | 4 |
| SambaNova SN50 | M | M | M | M | M | M | L | 3 |
| Tenstorrent Blackhole | L | none | none | M | L | L | L | 4.5 |
| d-Matrix Corsair | L | none | none | M | L | L | L | 4 |
| Etched Sohu | M | H | H | H | M | M | L | 2 |
| MatX One | n/a | H | H | H | M | M | L | 2 |
| Positron Asimov | n/a | none | none | M | L | L | L | 4 |
| Taalas HC1 (now AMD) | L | none | none | L | L | L | L | 4.5 (narrow use) |
| Rebellions REBEL (Samsung) | none | none | H | M | M | M | L | 3 |
| FuriosaAI RNGD | M | H | M | M | L | L | L | 2.5 |
| Qualcomm AI200, AI250 | n/a | none | none | M | M | M | L | 4 |
| Huawei Ascend (SMIC) | none | none | H | M | L | H | H | 2 (inside China) |
| Other Chinese vendors | none (estimate) | none | H | M | L | M | H | 2 (inside China) |
Rubin CPX is out of the matrix: NVIDIA took it off its roadmap in March 2026[75][76].
The main reasons behind the scores, our estimate. Rubin and MI455X: N3/N2, CoWoS-L and HBM4, with racks of about 234 kW for Vera Rubin (estimate, Morgan Stanley) and up to about 600 kW for Kyber (reported)[30][31]. Cerebras sidesteps CoWoS and HBM but runs into N5 wafers and megawatts: about 23 kW per CS-3, 700 MW under contract[54][139]. LPX depends on DRAM only through DDR5, but needs many chips. Rebellions sidesteps TSMC and CoWoS through Samsung I-Cube S, but stays in the HBM queue. LPDDR and GDDR designs leave HBM behind, but land in the general DRAM shortage. Chinese vendors run into SMIC yields and HBM.
Method and sources
Figures in our facts registry were checked against their sources on 27 November 2026. Where only a retelling exists, the page names whose retelling it is. Analyst estimates and press reports carry their author’s name, so they are not mistaken for what the companies themselves said. A cell of the appendix that no source we checked supports says “No data”.
Corrected on 25 November 2026: two memory cells of the appendix cited sources that did not give their figures. AWS Inferentia2 keeps 32 GB of HBM, now with AWS as the source[120]; FuriosaAI RNGD now shows 48 GB of HBM3, from the company's page[161], in place of two 24 GB stacks. The change is in our corrections log.
Updated on 26 November 2026: under “What this means for buyers” we added TrendForce’s outlook of 25 November for DRAM contract prices in 2027 and 2028 and the lead times for new B300 orders, and the closing line now says that waiting for lower prices means waiting at least through 2027. The change is in our corrections log.
Updated on 27 November 2026: under “What this means for buyers” we added TrendForce’s outlook of 27 November, a base case with DRAM contract prices falling from early 2028 and a bear case with a fall from late 2027, and the closing line now says that waiting is a bet on the bear case: it used to say that waiting for lower prices means waiting at least through 2027. Under “Export controls” we added China’s extensions of 9 and 24 November. The change is in our corrections log.
Many figures are analyst estimates or press reports (Economic Daily News, Commercial Times, Digitimes, retellings of Morgan Stanley and SemiAnalysis). TSMC gives no CoWoS capacity or prices in numbers: on its call for the third quarter of 2026 it described CoWoS only in words[210]. Figures from secondary aggregators (Tech-Insider, TechTimes, Introl, presenc.ai, Sacra, Spheron, BigGo) are pointers, not confirmation. The ranking, the verdicts, the dependency scores and the scenario probabilities are our estimate.
Ancapex introduces companies that need reserved GPU capacity to the operators that have it. How we are paid is in our methodology.
Sources
- SK hynix: Q3 2026 business results (press release, 28 Oct 2026)
- Samsung Electronics Announces Third Quarter 2026 Results (press release, 29 Oct 2026)
- Micron Q4 FY26 Prepared Remarks (30 Sep 2026)
- TSMC CoWoS Supply-Demand Gap Reportedly Seen Narrowing from 20% to 10% by End-2026 as Capacity Expands (TrendForce, 15 Jun 2026)
- TSMC Reportedly Targets 22% 2nm, 16%+ 3nm Capacity Boost by Mid-2027; CoWoS to Double by 2028 (TrendForce, 14 Sep 2026)
- Samsung Says HBM Share Matches DRAM Standing as HBM4 Sales Triple (TrendForce, 29 Oct 2026)
- TrendForce DRAM Bulletin (18 Nov 2026)
- Cuts to Chinese CSP Demand Weigh on Price Outlook, Slowing Memory Industry Revenue Growth in 2027 (TrendForce, press release, 25 Nov 2026)
- DRAM Demand Concerns Mount, Raising Risk of Contract Price Declines in 2028 (TrendForce, report summary, 25 Nov 2026)
- Limited Demand Visibility and Growing Supply Chain Caution Heighten Risk of DRAM Contract Price Declines in 2028 (TrendForce, press release, 27 Nov 2026)
- TrendForce: NAND Flash contract prices in Q1 2027 (press release, 19 Nov 2026)
- Sightline Climate (currence.ai): 2026 Data Center Outlook (24 Feb 2026)
- Up to half of the world's data centers may be delayed this year (Latitude Media, 24 Feb 2026)
- America's AI Build-Out Hinges on Chinese Electrical Parts (Bloomberg, 1 Apr 2026, archived copy)
- Mind the gap: tackling supply chain challenges in the electric T&D sector (Wood Mackenzie, 15 Oct 2025)
- US power companies scramble to secure equipment as data center demand surges (Reuters via Kitco, 9 Jul 2026)
- NVIDIA B300 Lead Times Reportedly Hit 40 Weeks; RTX 60 May Face Delays as Memory Supply Tightens (TrendForce, 25 Nov 2026)
- Morgan Stanley, September revision of CoWoS demand (cnyes, 12 Sep 2026)
- Unimicron Warns of IC Substrate Crunch: Up to 30-Month Equipment Lead Times, 20% Material Gap in 2027 (TrendForce, 20 Oct 2026)
- HBM market shares in Q2 2026 by Counterpoint (SamMobile, 3 Sep 2026)
- Samsung, SK hynix memory stockpiles fall below 10 days (Seoul Economic Daily, 7 Sep 2026)
- TrendForce: average HBM price in 2027 (press release, 29 Sep 2026)
- DRAM Prices Seen Rising 20% QoQ in 4Q26 Despite Slower Gains (TrendForce, 20 Oct 2026)
- Will the AI spending surge trigger an unprecedented memory chip shortage? (Korea JoongAng Daily)
- Micron says the silicon gap between HBM and DDR5 is widening with every generation (Tom's Hardware)
- Sightline Climate launches PowerStack newsletter (press release in Utility Dive, 5 Mar 2026)
- ERCOT's large load queue has nearly quadrupled in a single year (Latitude Media, 3 Dec 2025)
- Powering AI: Energy Market Outlook 2026 (Morgan Stanley, 27 Feb 2026)
- Morgan Stanley: 70 GW data center power shortfall (Crypto Briefing, 1 Nov 2026)
- Morgan Stanley on rack power and energy (BigGo Finance)
- NVIDIA GPU Roadmap 2026-2030: Rubin, Rubin Ultra, Feynman (VRLA Tech)
- TrendForce: CoWoS-L and EMIB-T in AI accelerators (press release, 18 Sep 2026)
- TSMC Says CoWoS Offers Industry's Largest Packaging Amid Intel EMIB Rivalry; CoPoS Advances (TrendForce, 16 Apr 2026)
- After TSMC's 3Q26 Earnings: Key Brokerage Takeaways as 2028 Capex Forecasts Reach US$105B (TrendForce, 16 Oct 2026)
- TSMC Reportedly Eyes Up to 15% 3nm Price Hike in 2H26, Further 5%-10% Seen in 2027 Amid AI, ASIC Demand (TrendForce, 27 May 2026)
- TSMC 2nm AI Chip Allocation 2026 (presenc.ai)
- Following Samsung, will TSMC raise prices by 10-15% across all process nodes? (Bitget)
- Shortages of crucial chip packaging material threatens AI accelerator supply chains (Tom's Hardware)
- IC substrate shortage to persist in 2026, AI and memory customers sign long-term contracts (Digitimes, 20 Nov 2025)
- Nitto Boseki raises its forecast and expands T-glass output (TechNews, 6 Nov 2026)
- T-glass shortage (CENS, 19 Jan 2026)
- AI Data Center Optical Component Shortage: Nvidia's $4B Laser Lockup Pushes Rivals Past 2027 (TechTimes, 27 May 2026)
- BIS rule of 15 Jan 2026, Federal Register 91 FR 1684, document 2026-00789
- BIS H200 Export Policy China: Case-by-Case Review 2026 (Introl)
- BIS H200 Export Policy Shift & AI OVERWATCH Act (Introl)
- China suspends ban on rare earth exports to US, but licensing remains (Tom's Hardware)
- MOFCOM Announcement No. 59 of 2026: the suspension of clause 2 of Announcement No. 46 of 2024 continues from 28 Nov 2026 to 27 Jan 2027 (Ministry of Commerce of China, 24 Nov 2026, in Chinese)
- China continues suspending part of control measures on dual-use items export to U.S. (Xinhua, 24 Nov 2026)
- MOFCOM and GAC Announcement No. 58 of 2026: the export control announcements of 2025 stay suspended from 11 Nov 2026 to 10 Jan 2027 (Ministry of Commerce of China, 9 Nov 2026, in Chinese)
- China extends suspension of rare earth export controls until January (Reuters in The Star, 9 Nov 2026)
- Huawei Pulls Ascend 960 Three Quarters Early (TechTimes, 17 Sep 2026)
- Intel Corp. Form 8-K, Q2 2026 results (SEC)
- Cerebras Announces Third Generation Wafer-scale Engine (Cerebras, 13 Mar 2024): 44GB on-chip SRAM
- Cerebras Systems Inc. Form 8-K, Q3 2026 results (SEC, 12 Nov 2026)
- Cerebras Systems Inc. Form 10-Q, quarter ended 30 Jun 2026 (SEC)
- Nvidia's Jensen Huang Thanks Samsung as It Manufactures 'Groq 3' AI Inference Chips (The Elec)
- NVIDIA Groq 3 LPU Explained: How the Non-GPU Inference Chip Changes AI Cloud Economics (Spheron)
- Samsung Foundry to Handle Full Production of Nvidia's 'Grok 3': 4nm Line at Full Capacity Fuels Profit Hopes (BigGo Finance)
- The Next Trillion-Dollar Chip Company (Chipstrat, Austin Lyons)
- d-Matrix Corsair, Hot Chips 2025 slides
- d-Matrix ramps Corsair AI inference platform into full production (Converge Digest, 9 Jun 2026)
- Research Note: Qualcomm Introduces AI200 & AI250 for Data Center Inference (NAND Research)
- Top AI Chip Companies: NVIDIA Alternatives Compared (Cloudzy Blog)
- Intel Crescent Island 160GB to 480GB LPDDR5X AI GPU at Hot Chips 2026 (ServeTheHome)
- AMD completes acquisition of AI inference chip company Taalas (Let's Data Science, 17 Nov 2026)
- AMD Acquires Taalas to Advance Compute Solutions for Rapidly Growing AI Inference Market (AMD, 6 Aug 2026)
- Can China Make 5nm Chips? (Semiecosystem)
- Samsung Foundry Starts Mass Production of Nvidia's Groq3 AI Chip (Seoul Economic Daily, 25 Aug 2026)
- Samsung's fab roadmaps examined: Taylor, Pyeongtaek, and the yield woes behind a $16.5 billion Tesla deal (Tom's Hardware)
- Intel Q2 2026 Prepared Remarks, CEO Lip-Bu Tan and CFO
- NVIDIA Corp. Form 8-K, Q3 FY2027 results (SEC, 17 Nov 2026)
- Deep dive into Azure Maia 300 architecture (Microsoft Azure Blog, 12 Oct 2026)
- Microsoft, blog post on Maia 300 (deployment from 2027)
- Intel Foundry Reportedly Secures 18A Order from Microsoft for Maia 3 Accelerator (Design & Reuse)
- How Nvidia's $20 billion Groq 3 LPU deal reshapes the Nvidia Vera Rubin Platform (Tom's Hardware)
- NVIDIA Rubin CPX Is Off The Roadmap, But May Return With Feynman In 2028 (Wccftech, 19 Mar 2026)
- Morgan Stanley Report: CoWoS Demand to Double by 2027, Driven by AMD and ASICs in AI Chip Growth (KuCoin)
- Nvidia says Groq racks will be online this year following $20 billion purchase (CNBC, 24 Aug 2026)
- Groq among the first to bring NVIDIA Groq 3 LPX and Vera Rubin NVL72 to market (Groq)
- Nvidia CEO says its advanced packaging technology needs are changing (Reuters in The Star, 16 Jan 2025)
- NVIDIA HGX (nvidia.com)
- NVIDIA GB200 NVL72 (nvidia.com)
- TrendForce: B300 and GB300 on CoWoS-L (press release, 22 Oct 2024)
- NVIDIA Vera Rubin NVL144 Servers Set for 2026 Volume Production (TechPowerUp, October 2025)
- Advanced Packaging Demand Soars: Nvidia Secures 60% of CoWoS Capacity (Astute Group)
- NVIDIA Corp. Form 8-K, Q2 FY2027 results (SEC, 26 Aug 2026)
- NVIDIA's Rubin Ultra Seen Sticking to Dual-Die Design on Packaging Constraints (TrendForce, 1 Apr 2026)
- Samsung Foundry begins full mass production of Nvidia's Groq 3 LPX chip (SamMobile)
- NVIDIA Groq 3 LPX (nvidia.com)
- NVIDIA Groq 3 LPX Now in Full Production (NVIDIA Newsroom, 24 Aug 2026)
- Groq and NVIDIA Enter Non-Exclusive Inference Technology Licensing Agreement (Groq, 24 Dec 2025)
- AMD details Instinct MI350: 3D chiplet, 185B transistors, 288GB HBM3E, TSMC N3P node (TweakTown, 26 Aug 2025)
- AMD Form 8-K, Q3 2025 results (SEC, 4 Nov 2025)
- AMD Unveils MI455X Targeting NVIDIA Rubin; TSMC 2nm, CoWoS-L Demand Seen Rising (TrendForce, 24 Jul 2026)
- AMD MI450 GPUs: Helios Ships 50,000 to Oracle (shattered.io)
- Inside AMD Advancing AI 2026: Lisa Su Puts Helios on Stage (technologyconference.com)
- AMD Form 8-K, Q3 2026 results (SEC, 3 Nov 2026)
- AMD Instinct MI450 Helios 2026: Is ROCm Finally CUDA-Ready? (AI Learning Guides)
- AMD Unleashes 'Helios' AI Flagship with 2nm GPU and CPU (BigGo Finance)
- AMD's Helios AI Rack Enters Full Production, Ships to Microsoft Azure in Q3 2026 (GamesReviews.com)
- Intel Gaudi 3 AI Accelerator White Paper
- Intel Corp. Form 10-K for 2025 (SEC)
- Intel chip roadmap 2026-2028 (Tom's Hardware, 16 Mar 2026)
- TPUv7: Google Takes a Swing at the King (SemiAnalysis)
- Ironwood: The first Google TPU for the age of inference (Google, 9 Apr 2025): 9,216 chips, nearly 10 MW
- Google's TPU Supply Chain (Data Gravity, 2 Jun 2026)
- Cloud TPU release notes (Google Cloud)
- Google begins allocating TPU orders; is AMD poised to take business from Broadcom? (moomoo)
- Google launches Ironwood TPU and previews eighth-gen split into training and inference chips at TSMC 2nm (TheNextWeb, 22 Apr 2026)
- Google splits its TPU into two chips for the first time, with training and inference variants (Tom's Hardware, 27 Apr 2026)
- Google a major Intel Foundry customer: EMIB advanced packaging for next-gen TPU (Wccftech, 27 Apr 2026)
- Amazon's AI chip (The Register, 3 Dec 2024)
- Amazon's AI Self Sufficiency: Trainium2 Architecture & Networking (SemiAnalysis)
- Trainium2 architecture (AWS Neuron documentation)
- Top 30+ AI Chip Makers: NVIDIA & Its Competitors (AIMultiple)
- TSMC Copies Intel's Packaging Approach: New EMIB-Like Program With Kinsus Shakes Up AI Race (TechTimes)
- Why Broadcom and Marvell Are The Real Winners Of The AI Chip War (INDmoney)
- AWS's Trainium3 Reportedly Draws Strong Interest From Large, Mid-Sized Clients (TrendForce, 31 Oct 2025)
- With Trainium4, AWS Will Crank Up Everything But The Clocks (The Next Platform, 3 Dec 2025)
- Amazon Inferentia (AWS)
- Inside Maia 100 (Microsoft Azure Infrastructure Blog, 27 Aug 2024)
- Microsoft Takes On Other Clouds With Braga Maia 200 AI Compute Engines (The Next Platform, 28 Jan 2026)
- The Custom AI Chip Race 2026: Big Tech vs Nvidia (NerdLevelTech)
- Microsoft's Clea Maia 300 Inference XPU Is A Bandwidth Beast (The Next Platform, 13 Oct 2026)
- Hyperscaler Custom Silicon Tracker 2026 (presenc.ai)
- OpenAI Titan Custom AI Chip: Samsung HBM4 Deal (Tech Insider)
- Tesla AI5 Tape-Out: 5x AI4 Power, Optimus Pivot (Tech Insider)
- The Node Flip: Tesla's AI5 Tape-out at Samsung Taylor Makes the 2027 Production Clock Real (Korean Tech Texas)
- Samsung Semiconductor Spotlight: HBM4, SF2 Foundry, DRAM Dominance & Taylor Texas (SemiconductorX)
- Samsung Taylor Fab's Equipment Move-In and the New AI4+ Chip Reshaping Every Tesla Delivery (Tesla Accessories blog)
- Samsung's Texas fab enters production for Tesla's AI5 chip on 2nm (Electrek, 13 Jul 2026)
- Tesla's Dojo training tile in production at TSMC (eeNews Europe, 6 May 2024)
- The Tesla Dojo Chip Is Impressive (SemiAnalysis)
- Elon Musk says Tesla's restarted Dojo3 will be for space-based AI compute (TechCrunch, 20 Jan 2026)
- Exclusive: ByteDance developing AI chip (Reuters via Yahoo Finance, 11 Feb 2026)
- Cerebras Systems Inc. Form 8-K, results announcement (SEC)
- Cerebras Systems Inc. Form 8-K, Q2 2026 results (SEC)
- AMD and Cerebras Announce Ultra-Low Latency and High Throughput AI Inference Solution (AMD, 23 Jul 2026)
- Cerebras WSE-3 (The Register)
- SambaNova SN50 RDU, datasheet
- Tenstorrent in talks with TSMC, Samsung, even Rapidus, for 2nm (SemiWiki)
- Tenstorrent vs NVIDIA 2026: Blackhole Specs, $110K Price (Spheron)
- Samsung to fab RISC-V chips for Tenstorrent (The Register, 2023)
- AI Chip Market Funding News (September 2026) (New Market Pitch)
- Etched (etched.com)
- Etched Sohu (aiwiki)
- Etched $300M Sohu Chip Rivals Nvidia H100 (TechPillow)
- Inference chip startup Etched raises another $700M at $21B valuation (SiliconANGLE, 18 Aug 2026)
- MatX (Sacra)
- MatX: Series B (matx.com, 24 Feb 2026)
- Startup takes on Nvidia with FPGA-based AI (EE Times Asia, 26 Feb 2025)
- Positron (positron.ai)
- Taalas: Products (taalas.com)
- Rebellions Accelerates Next-Gen AI Chip Production Featuring Four Samsung HBM3E (TrendForce, 23 Aug 2024)
- Samsung Foundry to make 2nm GAA chips for AI chip firm Rebellions (SamMobile)
- Samsung Foundry and Rebellions: ATOM on 5nm (SamMobile, 9 Oct 2023)
- Rebellions redefines energy-efficient AI (Synopsys, 22 Dec 2025)
- Rebellions REBEL100 (rebellions.ai)
- FuriosaAI RNGD at Hot Chips 2024 (ServeTheHome)
- FuriosaAI starts mass production of RNGD (Korea Herald, 2 Apr 2026)
- Furiosa RNGD PCIe Card (FuriosaAI)
- Graphcore Goes 3D With AI Chips (The Next Platform, 3 Mar 2022)
- Graphcore (graphcore.ai)
- Lightmatter Unveils Passage M1000 Photonic Superchip (Lightmatter)
- Lightmatter Passage M1000 EVK (Lightmatter)
- Lightmatter Passage L200 (Lightmatter)
- Axelera AI Europa AIPU (axelera.ai)
- Axelera AI unveils Titania architecture (axelera.ai, 12 Nov 2026)
- Axelera AI launches Europa (axelera.ai, 15 Sep 2026)
- Blaize (blaize.com)
- EnCharge AI (enchargeai.com)
- Hailo Technologies (Wikipedia)
- Mythic (mythic.ai)
- American chip giant AMD to acquire Untether AI team (BetaKit, 6 Jun 2025)
- Esperanto Technologies (esperanto.ai)
- OpenAI acquires Rain AI patents after takeover talks fail (crypto.news, 6 Aug 2026)
- Extropic (extropic.ai)
- Hygon, 2025 annual report (cninfo)
- Biren, HKEX prospectus (22 Dec 2025)
- Where China's AI chip supply chain stands in 2026 (The Substrate, 2 Jun 2026)
- Huawei Ascend Production Ramp: Die Banks, TSMC Continued Production, HBM is The Bottleneck (SemiAnalysis)
- Huawei to double output of Ascend AI chips (RCR Wireless)
- Huawei Ascend 950PR: The 1.56 PFLOP AI Chip vs Nvidia (Tech Insider)
- Huawei Debuts Atlas 350 on Ascend 950PR with In-house HBM, Touting 2.8X H20 Performance (TrendForce, 23 Mar 2026)
- Big Chinese tech firms scramble to secure Huawei AI chips after DeepSeek V4 launch (Reuters via Khaleej Times, 29 Apr 2026)
- DeepSeek V4 on Huawei's Ascend 950: A Real Stress Test for China's AI Chip Ecosystem (DEV Community)
- Huawei Connect 2025, keynote by Eric Xu (huawei.com)
- Huawei Brings Forward Ascend 950DT Deployment to August (TrendForce, 8 Jun 2026)
- Cambricon Remains China's Top AI Chip Startup (TrendForce, 15 Dec 2025)
- Cambricon MLU590 (Flopper)
- China AI Weekly: DeepSeek's 160K Huawei Chip Megaproject (Big Hat Group, 6 Sep 2026)
- Alibaba T-Head PPU Lands China Unicom Deal (TrendForce, 17 Sep 2025)
- Alibaba T-Head Unveils Zhenwu M890 (TrendForce, 21 May 2026)
- China's AI Chip Landscape: A Complete Map of Who's Building What (Crossing River)
- Baidu Kunlunxin P800 AI accelerator: interconnect and packaging analysis (TechInsights, 7 May 2026)
- Kunlunxin P800 (UDN, 20 Jul 2026)
- Moore Threads MTT S5000 (en.mthreads.com)
- Moore Threads (Wikipedia)
- Silicon Vanguard: Ranking China's Domestic Chip Leaders (Machine Yearning)
- Iluvatar CoreX TianGai 150 (iluvatar.com)
- Tencent Zixiao 2.0 (36Kr, 7 Sep 2026)
- Qualcomm Cloud AI 100 Ultra (Flopper)
- Qualcomm Cloud AI 100 Ultra, Product Brief
- Qualcomm Dragonfly AI200 (qualcomm.com)
- CoWoS allocation by customer, 2026-2027 (36Kr, 13 Jul 2026)
- Morgan Stanley: AI Supply Chain, Prelim 2028 AI semis vs. CSP capex growth (Zhitong via Webull)
- Google in talks with Marvell Technology to build new AI inference chips alongside Broadcom TPU programme (TheNextWeb)
- LLM Inference Hardware: An Enterprise Guide to Key Players (IntuitionLabs)
- Ironwood chetyorka: Google, Broadcom, MediaTek, and TSMC (Jon Peddie Research)
- TSMC, Q3 2026 quarterly results