Ancapex Research: reserved GPU demand and start dates

Monthly report and weekly index · Updated 16 November 2026

Every month we count what buyers of reserved GPU capacity ask us for: the GPU model, cluster size, term, start and region. Every week we track when operators can start each model. The figures come from the requests and offers that reach Ancapex, combined so that no company can be picked out.

Latest report
GPU Demand, October 2026, recounted 16 November 2026
Next report
Reserved GPU Demand, November 2026, out in early December 2026
Every figure
At least 3 different buyers, or 5 different operators for start dates
Never published
Names, single requests or offers, prices
Who pays us
Operators, about 1.5% of the value of a contract we introduce. Buyers pay us nothing directly.

Monthly report: Reserved GPU Demand

What buyers asked us to reserve in a calendar month, and when operators could start, published in the first days of the next month. An issue stays as it was published; corrections go into the log with their date.

GPU Start Date Index

When operators in our pipeline can start reserved capacity, by GPU model: the median month, from at least 5 operators per model. Updated every week, normally on Monday. Formerly the B300 Price Index.

Data

Groups below our thresholds are not in the files either. You may quote the figures with a link to the page they come from.

How we count

These are the requests and offers that reach Ancapex, not the whole market. Before counting we leave out clients under NDA, requests from partners and intermediaries, and offers from operators that signed our agreements. The report says what buyers asked for and when operators can start, never what anyone should charge.

Press and analysts

Questions about a figure or the method go to Dmitriy Kim, Co-Founder of Ancapex: dima@ancapex.io.

To cite: Ancapex Research, GPU Demand, October 2026, https://www.ancapex.io/guides/gpu-demand-october-2026.